Home/How to Write a Construction Change Order
Construction change orders

Construction Change Order: What It Is, How to Write One, and Getting It Paid

A construction change order is a written amendment to the contract that changes the scope, the price or the schedule, signed by both sides. Below: what goes on one, a worked pricing example, and the part most templates skip, which is getting the approved change into the job budget and onto the next invoice.

The short version

What it is: a signed change to the original contract. It says what's added, removed or swapped, what that costs, and how many days it adds.

Who signs: the owner (or the architect for them) and the contractor. When a sub's scope changes, the GC and the sub sign their own change order too.

When: before the extra work starts, unless the contract lets the owner direct the work in writing while the price is settled.

How to write a change order, field by field

Whether you use an AIA G701, your software's form or your own template, these are the parts that matter.

  1. 1

    Header: project, contract and number

    Project name, the contract it amends, the date, and a change order number. Number them in sequence and never reuse one, even for a rejected change, so every number in the log means exactly one thing.

  2. 2

    Describe the change and what caused it

    Say what's changing, where, and why. Reference the drawing revision, RFI, site condition or owner email that triggered it.

    Watch for: scope written as "additional electrical work". Name the fixtures, the rooms and the drawing sheet, so nobody can argue about it at closeout.

  3. 3

    Price it

    Labor hours and rate, materials, equipment, subcontractor quotes, then overhead and profit at the rate your contract allows. Attach the sub quotes.

    Watch for: the markup clause. Many contracts cap overhead and profit on changes, and some set different rates for your own work and for subcontracted work.

  4. 4

    State the time

    Write the number of days added to the contract time, or "no change". A blank here makes it hard to ask for the time later.

  5. 5

    Show the new contract sum

    Original contract sum, net change from earlier approved change orders, this change, and the new total. Anyone reading it should see the running total without opening the log.

  6. 6

    Get both signatures before the crew starts

    Owner and contractor, plus the architect on most AIA contracts, each with a date. Some contracts accept email approval, but a signature settles the question.

  7. 7

    Put it in the budget and the schedule of values

    Add the change to the job's budget lines and as a new line on the schedule of values, so it's billed on the next pay application. This is the step that gets skipped.

Pricing one change order, line by line

Four extra recessed lights and a dimmer, asked for after the ceiling was finished.

Example only. Rates and markup here are illustrative, so use your own and your contract's.
Electrical labor, 10 hours at $85 $850
Fixtures, dimmer, wire and boxes $620
Drywall patch and paint, sub quote $480
Overhead and profit at 15% of $1,950 (rounded) $293
Change order total (plus 1 day to the schedule) $2,243

The drywall sub's $480 also needs its own change to their subcontract, or job cost will show a profit the job doesn't have.

Change order request or change order?

People use the words loosely. The difference decides whether you can bill it.

Proposed

Change order request (or PCO)

  • Your proposal: scope, price and time, sent for approval.
  • Doesn't change the contract yet, so it can't go on a pay app.
  • Belongs in the log as pending, with the date it was sent.
Agreed

Change order

  • Signed by both sides, so the contract sum and time change.
  • Added to the budget and the schedule of values.
  • Billed on the next pay application.

When work has to start before the price is agreed, AIA contracts use a Construction Change Directive (G714) instead of a Change Order (G701). The work goes ahead and the price is settled later, which is exactly when tracking slips most.

Why approved changes still don't get paid

A good template doesn't help with any of these. They happen after the signature.

Signed in the field, unknown in the office

How you'll know: The PM has a signed PDF on a tablet. The budget in accounting still shows the original contract.

Fix: When the change order is signed, its lines go into the job budget and the schedule of values with the PDF attached, without anyone keying them.

The sub's side never moves

How you'll know: The owner's change is priced, but the subcontract and committed cost stay at the old number, so job cost looks healthier than it is.

Fix: Create the matching subcontract change or commitment change from the same approval.

Pending requests nobody totals

How you'll know: A dozen change order requests are waiting on the owner and nobody can say what they're worth or how old they are.

Fix: A weekly list of pending requests by age and value, sent to the PM and the owner's rep.

Three totals at closeout

How you'll know: The log, the budget and billed-to-date each show a different figure for approved changes.

Fix: One record per change order that the log, the budget and billing all read from, so the totals can't drift apart.

Questions people ask

What is a change order in construction?

A written, signed amendment to the construction contract that changes the work, the price, the schedule, or all three. Until it's signed it's a request, and it can't be billed.

Who prepares a change order?

Usually the contractor prices and writes it, and the owner or architect reviews and signs. On subcontracts, the GC issues the change order to the sub.

Can a contractor do extra work without a signed change order?

They can, but getting paid for it gets harder. Most contracts require changes in writing, and some say unapproved extra work isn't owed. Read the changes clause, and at minimum get a written directive before the crew starts.

Do you build the change order form itself, or just connect it?

Connect it, in most cases. Most teams have a change order form they're used to. The gap is getting the approved result into the budget and billing on its own, not changing how the form is filled in.

What about submittals, is that the same thing?

Close cousins, not the same. Submittals are documents reviewed and approved before work is installed. Change orders change scope and cost during the job. Our submittal log page covers that process.

Does this work with our existing construction software?

Yes. We build around what you already run, whether that's Buildertrend, Procore or another platform, and connect its change order approvals to your actual budget and billing.

Is the quote really free with no obligation?