What is the difference between Asana's Timeline and Calendar views?
Calendar view puts tasks on a month or week grid by due date, with no dependency logic, and it's on every plan. Timeline is the Gantt-style chart, with tasks as bars, dependency lines between them and milestones, and it starts on the Starter plan.
Can I sync my Asana calendar with Google Calendar or Outlook?
Yes, one way. Use Export, then Sync to calendar from the project menu, and paste the link into Google Calendar (add from URL) or Outlook (subscribe from the web). Changes made in your calendar app don't flow back to Asana. On paid plans, Asana's Outlook Calendar app syncs task times rather than all-day events.
How do milestones work in Asana?
A milestone is a task marked as a milestone. It stands for a moment, such as a launch or a deadline, rather than a stretch of work, so Timeline draws it as a diamond on one date. Other tasks can depend on it like any task.
Can Asana show a Gantt chart across multiple projects?
Not as one chart of every task. Timeline and Gantt each show one project, though a task can depend on a task in another project. To see a schedule that spans several projects, the dates have to be gathered from each one, by hand or with a script on the API.
Can I set a task dependency in Asana through the API?
Yes. Dependencies and start and due dates are ordinary task data in the Asana API, so you can read them and set them in code. That's how a bulk setup or a migration builds a full schedule without anyone dragging bars.
Does Asana's Timeline view require a paid plan?
Yes. Timeline and Gantt start on the Starter plan. The free Personal plan includes list, board and calendar views only.