Undated items
How you'll know: The chart ends in May. Everyone knows the launch is in July.
Fix: Filter the board for an empty Timeline and fill those items in. A rough range beats a missing bar, because a missing bar hides the tail of the project.
Someone in Thursday's meeting will ask, "if design runs late, when do we launch?" A monday.com Gantt chart can answer that, but only once three things are in place: a Timeline column, a Dependency column, and a dependency mode that matches how your work really behaves. Here's the setup, how to pick the mode, and what to do when the project doesn't fit on one board.
Click + next to the view tabs at the top of the board and choose Gantt. Every item with a Timeline value turns into a bar, and the board's groups show as bands. The view is on the Standard plan and above.
Watch for: items with an empty Timeline simply don't appear. A half-dated board gives you a chart that looks shorter than the real project.
Bars need a duration, which is what a Timeline column stores. A board that only tracks deadlines in a Date column won't give you proper bars, so add a Timeline column and fill it, even with rough dates to begin with.
Add the column, then on each item pick the item it's waiting for. The Gantt view draws an arrow between the two. When you set the column up, monday asks which time column the dependencies follow and which mode to use, and the mode is the choice that matters most.
Watch for: the Dependency column links items on the same board. Items sitting on other boards need a different approach, covered further down.
On Pro and Enterprise, the Gantt baseline saves a snapshot of the agreed schedule, so later you can see each bar's current position against where it started. Take it the day the plan is signed off. A baseline taken mid-project only tells you how far things moved since last Tuesday.
The mode decides what happens to later items when an earlier one moves. It only has an effect on boards with a Date or Timeline column.
How you'll know: The chart ends in May. Everyone knows the launch is in July.
Fix: Filter the board for an empty Timeline and fill those items in. A rough range beats a missing bar, because a missing bar hides the tail of the project.
How you'll know: One late item and a whole column of bars jumps a week, including work that could have started anyway.
Fix: Strict keeps every gap, so it pushes everything. If those tasks have slack, switch the column to Flexible, or remove the links that aren't real waits.
How you'll know: The client asks how late you are against the original plan, and the chart only shows today's dates.
Fix: On Pro or Enterprise, save a baseline now and note the date you took it. On other plans, copy the agreed dates into a second Timeline column before work starts.
How you'll know: A crane hire, an inspection slot or a client's go-live window gets rebooked somewhere else, and the Gantt stays on schedule.
Fix: Give that date its own item, link the dependent work to it, and have it written by the system that owns it. Timeline and Dependency values are ordinary columns in monday's GraphQL API, the same one covered on the monday CRM API page, so a sync can set them.
Seeing several boards on one chart is the easy part. Put a Gantt widget on a dashboard and pick the boards, and it lays their items out together, with the critical path drawn in red across the items it shows. That's usually enough for a status meeting.
The harder part is movement. When the design item slips, nothing on the build board shifts, because the Dependency column can't link to an item on another board. monday has a separate cross-project dependencies feature for project boards, so check whether your account has it. If it doesn't fit, n-frames builds a small service that listens for Timeline changes through monday's webhooks, applies the same rule a Strict link would (keep the gap, or only push on overlap), redates the waiting items on the other board, and posts a note on each item it moved, so the change is never a mystery.
Add a Dependency column, then link each item to the item it waits for, and the Gantt view draws an arrow between them. The column's mode decides what happens next: Strict moves later items by the same amount, Flexible only pushes them when they'd overlap, and No action leaves the dates alone.
Yes, with the Gantt widget on a dashboard, which lays out items from the boards you choose on one chart. What it doesn't do is make items on different boards push each other's dates, since the Dependency column only links items on the same board. A cross-board date rule needs monday's cross-project dependencies feature, where your account has it, or a script on the API.
Yes. Timeline view lays items on a time axis grouped by person, status or group, which suits "what's coming up". The Gantt view is the project-plan version: groups as bands, dependency arrows, the critical path, and baselines on Pro and above. Both read the same Timeline and Dependency columns.
Yes. The Dependency column is readable and writable through monday's GraphQL API, like the Timeline column. That's how a migration or a bulk setup links hundreds of items without anyone clicking through them, and how n-frames carries date changes from one board to another.
For linked items on the same board, yes, according to the mode. Strict moves later items in either direction, Flexible pushes them only to stop an overlap, and No action moves nothing. A late item on another board, or a date that changed outside monday.com, won't show up until someone or something updates it.