How do dependencies work in monday.com?
Add a Dependency column, link an item to the item it depends on, and the Gantt view draws a connecting arrow between them. Move the predecessor's end date and everything downstream that depends on it shifts automatically.
Can monday.com show a Gantt chart across multiple boards?
Not natively in one unified view. The Gantt chart renders one board's timeline at a time. Seeing a true cross-board critical path takes either a connected-boards setup with manual review or custom work that pulls timeline data from several boards into one combined view.
Is there a difference between monday.com's Timeline view and its Gantt view?
Timeline view is the simpler bar-chart layout without dependency arrows. Gantt view adds the dependency lines and the automatic date-shifting when a predecessor moves. Both read from the same underlying date and dependency columns.
Can I set a dependency on a monday.com item through the API?
Yes. Dependency and timeline data are stored as ordinary board columns, both fully readable and writable through monday's GraphQL API, so scripting dependencies at scale, say during a migration, is genuinely possible.
Does the Gantt view update automatically when a task finishes early or late?
Yes, for dependent items on the same board, moving one item's dates reflows anything downstream of it automatically. It only reflows what the Gantt view can see, so a delay on a different board, or a delay caused by something outside monday.com, won't show up until someone updates the date by hand.