Home/Wrike/Wrike Gantt Dependencies and the Critical Path
Wrike

Reading a Wrike Gantt Chart: What Moves When a Task Slips, and What Can't Wait

The review got pushed a week, and you need to know whether launch moves with it. Wrike's Gantt chart can tell you, as long as the tasks are linked and your plan includes critical path. Team gets the chart and dependencies. Critical path, float and baselines start at Business.

Wrike Gantt features by plan

Gantt chart and dependencies: Team, Business, Pinnacle and Apex. Not on Free.

Critical path: Business and up. Open the project in Gantt Chart view, then the three-dot menu on the toolbar.

Gantt Chart ⋯ Critical path

Baselines: Business and up, from the same menu in Gantt Chart or Table view. You need the Set baseline permission.

Gantt Chart ⋯ Set baseline

Who can use them: Collaborators, Contributors and Viewers can't turn on critical path, so a PM on one of those seats won't see the option.

Turning a list of dated tasks into a schedule Wrike can push

  1. 1

    Draw the links between bars

    In Gantt Chart view, hover a task's bar and drag from its end to the task that waits on it. Finish to start is the usual one: B can't begin until A is done. Wrike also offers start to start, finish to finish and start to finish for work that overlaps.

    Watch for: a dependency moves dates only. It won't set the next task to In progress when the first one completes; that takes an automation rule or a custom workflow.

  2. 2

    Add lead or lag where the gap is real

    A two-day cure, a week for the client to sign: Wrike lets you put lead or lag time on a link, so the wait survives a reschedule instead of collapsing to zero.

  3. 3

    Turn on critical path

    ⋯ Critical path

    Tasks where a one-day delay would push the project's finish show in red. Red doesn't mean late. It means there's no room. On the new Gantt chart, add Total float and Free float under Fields to see how many days each other task can give.

    Watch for: the red line changes as you edit dates, links and milestones, so look at it after every replan, not just once.

  4. 4

    Set the baseline on sign-off day

    ⋯ Set baseline

    Pick current dates, or past dates from the project's history if you forgot. Apply it to the whole project or only to items without one yet. The baseline fields then show up in Table view, dashboards and filters, so you can report variance.

    Watch for: each item holds one baseline. Setting a new one overwrites the old values and can't be undone.

What a Wrike slip reaches, and who it misses

Inside the project

Wrike handles this

  • Every active task downstream of the late one moves by the dependency rule.
  • Critical path and float update, so you see whether the finish date moved.
  • Assignees in Wrike see their new dates on their own work.
Outside it

Nobody gets told

  • The supplier booked for the old install date.
  • A team planning in another PM tool, or a resourcing sheet that still holds the old week.
  • The client portal or shared calendar that shows the launch date.

n-frames builds the piece on the right: when Wrike redates a task through its API, the people and systems that depend on that date get the change, with the old and new date side by side.

Questions people ask

Does Wrike have Gantt charts?

Yes. Gantt Chart is one of the views on any folder, project or space, on Team and higher plans. Tasks with dates show as bars, milestones as points, and dependencies as arrows between bars.

What dependency types does Wrike support?

All four: finish to start, start to start, finish to finish and start to finish. You can add lead or lag time to a link, and a date constraint can stop Wrike pulling a task earlier than a set date.

Can Wrike automatically notify people outside the tool when a dependency slips?

Only inside Wrike. It reschedules the dependent tasks and their assignees see the new dates, but a supplier, a client or a team in another system doesn't. n-frames builds that on Wrike's API: it watches for date changes on the tasks that matter and sends the new date wherever it needs to go.

Is Wrike's Gantt view available on every plan?

No. Free doesn't include it. Team gets the Gantt chart and dependencies. Critical path, float and baselines need Business, Pinnacle or Apex, and some user types can't use them even on those plans.

What does the red line on a Wrike Gantt chart mean?

That's critical path. Red tasks have no float, so a one-day delay on any of them pushes the project's finish date. It's a different thing from overdue.

A linked Wrike task that refused to move

It was already completed, deferred or canceled

How you'll know: The predecessor slipped and one task further down the chain kept its old date.

Fix: Wrike only reschedules active tasks. Anything completed, canceled, deferred or deleted is skipped, and the chain beyond it can look broken. Reopen it, or relink around it.

A date constraint is holding it

How you'll know: The task won't come earlier when its predecessor finishes early.

Fix: A date constraint sets the earliest a task can start, and Wrike won't pull it before that. Clear the constraint if the date isn't truly fixed.

The link points the wrong way

How you'll know: Moving the task you expected to drive the schedule pushes nothing, and moving its successor pushes it instead.

Fix: Open the dependency and check which task is the predecessor. Start to finish is the easy one to set by mistake.

The real deadline lives elsewhere

How you'll know: A delivery or permit date changed in another system, and the Gantt chart still shows the old plan.

Fix: Make that date its own milestone, link the dependent tasks to it, and have the system that owns it update it. The Wrike API can write task dates, so a sync can do that.